# Tracking SPIRV-Tools work with GitHub projects
|
||
|
|
||
|
We are experimenting with using the [GitHub Project
|
||
|
feature](https://help.github.com/articles/tracking-the-progress-of-your-work-with-projects/)
|
||
|
to track progress toward large goals.
|
||
|
|
||
|
For more on GitHub Projects in general, see:
|
||
|
* [Introductory blog post](https://github.com/blog/2256-a-whole-new-github-universe-announcing-new-tools-forums-and-features)
|
||
|
* [Introductory video](https://www.youtube.com/watch?v=C6MGKHkNtxU)
|
||
|
|
||
|
The current SPIRV-Tools project list can be found at
|
||
|
[https://github.com/KhronosGroup/SPIRV-Tools/projects](https://github.com/KhronosGroup/SPIRV-Tools/projects)
|
||
|
|
||
|
## How we use a Project
|
||
|
|
||
|
A GitHub Project is a set of work with an overall purpose, and
|
||
|
consists of a collection of *Cards*.
|
||
|
Each card is either a *Note* or a regular GitHub *Issue.*
|
||
|
A Note can be converted to an Issue.
|
||
|
|
||
|
In our projects, a card represents work, i.e. a change that can
|
||
|
be applied to the repository.
|
||
|
The work could be a feature, a bug to be fixed, documentation to be
|
||
|
updated, etc.
|
||
|
|
||
|
A project and its cards are used as a [Kanban
|
||
|
board](https://en.wikipedia.org/wiki/Kanban_board), where cards progress
|
||
|
through a workflow starting with ideas through to implementation and completion.
|
||
|
|
||
|
In our usage, a *project manager* is someone who organizes the work.
|
||
|
They manage the creation and movement of cards
|
||
|
through the project workflow:
|
||
|
* They create cards to capture ideas, or to decompose large ideas into smaller
|
||
|
ones.
|
||
|
* They determine if the work for a card has been completed.
|
||
|
* Normally they are the person (or persons) who can approve and merge a pull
|
||
|
request into the `master` branch.
|
||
|
|
||
|
Our projects organize cards into the following columns:
|
||
|
* `Ideas`: Work which could be done, captured either as Cards or Notes.
|
||
|
* A card in this column could be marked as a [PLACEHOLDER](#placeholders).
|
||
|
* `Ready to start`: Issues which represent work we'd like to do, and which
|
||
|
are not blocked by other work.
|
||
|
* The issue should be narrow enough that it can usually be addressed by a
|
||
|
single pull request.
|
||
|
* We want these to be Issues (not Notes) so that someone can claim the work
|
||
|
by updating the Issue with their intent to do the work.
|
||
|
Once an Issue is claimed, the project manager moves the corresponding card
|
||
|
from `Ready to start` to `In progress`.
|
||
|
* `In progress`: Issues which were in `Ready to start` but which have been
|
||
|
claimed by someone.
|
||
|
* `Done`: Issues which have been resolved, by completing their work.
|
||
|
* The changes have been applied to the repository, typically by being pushed
|
||
|
into the `master` branch.
|
||
|
* Other kinds of work could update repository settings, for example.
|
||
|
* `Rejected ideas`: Work which has been considered, but which we don't want
|
||
|
implemented.
|
||
|
* We keep rejected ideas so they are not proposed again. This serves
|
||
|
as a form of institutional memory.
|
||
|
* We should record why an idea is rejected. For this reason, a rejected
|
||
|
idea is likely to be an Issue which has been closed.
|
||
|
|
||
|
## Prioritization
|
||
|
|
||
|
We are considering prioritizing cards in the `Ideas` and `Ready to start`
|
||
|
columns so that things that should be considered first float up to the top.
|
||
|
|
||
|
Experience will tell us if we stick to that rule, and if it proves helpful.
|
||
|
|
||
|
## Placeholders
|
||
|
|
||
|
A *placeholder* is a Note or Issue that represents a possibly large amount
|
||
|
of work that can be broadly defined but which may not have been broken down
|
||
|
into small implementable pieces of work.
|
||
|
|
||
|
Use a placeholder to capture a big idea, but without doing the upfront work
|
||
|
to consider all the details of how it should be implemented.
|
||
|
Over time, break off pieces of the placeholder into implementable Issues.
|
||
|
Move those Issues into the `Ready to start` column when they become unblocked.
|
||
|
|
||
|
We delete the placeholder when all its work has been decomposed into
|
||
|
implementable cards.
|