update externally published milestone schedule

No-Try: true
Docs-Preview: https://skia.org/?cl=137388
Bug: skia:
Change-Id: I83e4da9722991d64190b5e6b73b87a8f9791d629
Reviewed-on: https://skia-review.googlesource.com/137388
Reviewed-by: Joe Gregorio <jcgregorio@google.com>
Commit-Queue: Heather Miller <hcm@google.com>
This commit is contained in:
Heather Miller 2018-06-25 13:01:30 -04:00 committed by Skia Commit-Bot
parent bdf985c761
commit 73aaf259d3

View File

@ -10,18 +10,18 @@ point, for the next six weeks, only high priority fixes are checked into the bra
After the six week period, when another branch is cut, only critical (typically
security) fixes will be committed to any previous branch.
Skia 2017 schedule:
Skia 2018 schedule:
Milestone | Branch Date (beginning of day)
----------|-------------------------------
57 | 01/19/17
58 | 03/02/17
59 | 04/13/17
60 | 05/25/17
61 | 07/20/17
62 | 08/31/17
63 | 10/12/17
64 | 11/30/17
65 | 01/18/18
66 | 03/01/18
67 | 04/12/18
68 | 05/24/18
69 | 07/19/18
70 | 08/30/18
71 | 10/11/18
72 | 11/29/18
The current milestone is included in the headers in
[SkMilestone.h](https://skia.googlesource.com/skia/+/master/include/core/SkMilestone.h).