Milestone Schedule
|
|
|
|
==================
|
|
|
|
|
|
|
|
On a six week cadence aligned with Chromium, Skia cuts milestone branches.
|
|
|
|
Clients wishing to stay on a relatively stable level of Skia often utilize these
|
|
|
|
branches.
|
|
|
|
|
|
|
|
On the branch date, a healthy level of Skia near HEAD is chosen. After this
|
|
|
|
point, for the next six weeks, only high priority fixes are checked into the branch.
|
|
|
|
After the six week period, when another branch is cut, only critical (typically
|
|
|
|
security) fixes will be committed to any previous branch.
|
|
|
|
|
2020-04-03 16:01:51 +00:00
|
|
|
Skia 2020 schedule:
|
2016-02-24 00:26:03 +00:00
|
|
|
|
2017-02-21 19:01:34 +00:00
|
|
|
Milestone | Branch Date (beginning of day)
|
|
|
|
----------|-------------------------------
|
2020-04-03 16:01:51 +00:00
|
|
|
81 | 01/30/20
|
|
|
|
82 | 03/12/20
|
|
|
|
83 | 04/02/20*
|
|
|
|
84 | 05/14/20
|
|
|
|
85 | 06/25/20
|
|
|
|
86 | 08/20/20
|
|
|
|
87 | 10/01/20
|
|
|
|
88 | 11/12/20
|
|
|
|
|
|
|
|
Note that 82 was abandoned by Chromium and 83 schedule moved in due to COVID-19 impact.
|
|
|
|
Skia is maintaining 82 for our customers. Future dates are subject to change.
|